Project Updates

Construction Update #34 – January 1, 2024

Construction Update #34 – January 1, 2024

The building has achieved occupancy #1-3, and will continue to undergo inspection until complete and all residence move in. As of January 2024 the building is substantially complete and partially occupied

Construction Update #33 – December 1, 2023

Construction Update #33 – December 1, 2023

Starting off December the building has been fully enclosed. Completion of overhead doors and exterior amenities is underway. 1st occupancy is now complete with suites going through PDI up to level 26. Interior finishes are ongoing throughout the lobby and amenity...

Construction Update #32 – November 1, 2023

Construction Update #32 – November 1, 2023

Moving into November the project continues to wrap up exterior landscaping work on level 6&8 terrace. The exterior hoist has also been removed allowing sidewalks to be installed along Mercer Street. All remaining precast and windows will be complete before the...

Construction Update #31 – October 1, 2023

Construction Update #31 – October 1, 2023

October introduces new milestones for 55 Mercer! The construction hoist is being dismantled, elevators turned on, completion of landscaping and building envelope. Equipment is already starting to be turned on and commissioned.

Construction Update #30 – September 1, 2023

Construction Update #30 – September 1, 2023

Wrapping up August was exciting with the removal of our tower crane. As we enter September, we are moving forward with level 6 & 8 outdoor amenities. All waterproofing, planters, basketball court and metal panel work are underway. Next, focusing on the interior...

Construction Update #29 – August 1, 2023

Construction Update #29 – August 1, 2023

August brings new activities to 55 Mercer, now with roofing activities on the amenity levels and flood testing almost complete. Planters are underway on level 6 & 8 that will be part of the future amenity spaces. Interior works ongoing with drywall, tile, and...

Construction Update #28 – July 1, 2023

Construction Update #28 – July 1, 2023

After topping off in June, progress throughout the building façade and envelope continue. Roofing, windows and metal panel installation are ongoing. Exterior and interior work on suites and amenities are moving forward with finishes.

Construction Update #27 – June 5, 2023

Construction Update #27 – June 5, 2023

The progress on site has reached the mechanical penthouse and elevator machine room. The final roof slab is set to be poured before the end of June bringing a close to the structure. Common areas are underway with framing and boarding, along with equipment deliveries.

Construction Update #26 – May 3, 2023

Construction Update #26 – May 3, 2023

Welcoming Spring, the landscaping along with North and West corridors are nearing completion with sidewalks, pavers, curbs, and irrigation now complete. Moving along the ground floor façade the curtain wall for the retail space is progressing well. The structure rests...

Construction Update #25 – April 3, 2023

Construction Update #25 – April 3, 2023

Moving into April the formwork is reaching the upper floors now on 42 and progressing. Windows now installed to 34. The landscaping on ground floor has reached the South, West and North side with irrigation, curbs, planters, and sidewalks taking place.