Welcoming Spring, the landscaping along with North and West corridors are nearing completion with sidewalks, pavers, curbs, and irrigation now complete. Moving along the ground floor façade the curtain wall for the retail space is progressing well. The structure rests on level 46 with the top floors remaining. Windows are installed to level 38.
Construction Update #26 – May 3, 2023
May 3, 2023