55 Mercer Condominiums
Construction Information
55 Mercer Condominiums Construction Information
Construction Update #34 – January 1, 2024
The building has achieved occupancy #1-3, and will continue to undergo inspection until complete and all residence move in. As of January 2024 the building is substantially complete and partially occupied
Construction Update #33 – December 1, 2023
Starting off December the building has been fully enclosed. Completion of overhead doors and exterior amenities is underway. 1st occupancy is now complete with suites going through PDI up to level 26. Interior finishes are ongoing throughout the lobby and amenity...
Construction Update #32 – November 1, 2023
Moving into November the project continues to wrap up exterior landscaping work on level 6&8 terrace. The exterior hoist has also been removed allowing sidewalks to be installed along Mercer Street. All remaining precast and windows will be complete before the...